Mar 29, 2011

Ithaca resumes Jacky drilling



– Ithaca Energy Inc. (TSX Venture: IAE, LSE AIM:  IAE) announces that drilling of the J03 well on the Jacky field has now recommenced, as previously stated.
The Energy Enhancer drilling unit is now fully operational following successful repair to the
drilling mud handling system onboard the rig. Production from J01 was briefly suspended to
complete the ‘top hole section’ of the J03 well and then immediately reinstated. The J03 well
has now been drilled to approximately 2,400 feet measured depth and drilling operations are
scheduled to last approximately a further 60 days.
Source: Ithaca Energy