Ithaca Energy Inc. Athena Field Development Operations & FPSO Modifications Progress as Planned




    Ithaca Energy Inc. and its wholly owned subsidiary Ithaca Energy (UK) Limited, an independent oil & gas company with exploration, development and production assets in the UK sector of the North Sea, announces that the Sedco 704 drilling unit is now being anchored on location over the Athena field ready to commence an approximate 180 day campaign to drill a fourth production well and a water injector well and complete the three existing wells on the field as producers.  In addition, modification and recertification of the Floating Production Storage and Offtake (“FPSO”) vessel (BW Athena) is well underway in a Dubai shipyard.  
The Sedco 704 drilling unit will initially drill one water injection well, followed by a fourth production well (three suspended appraisal wells are to be completed for production as part of this campaign). The four production wells will be installed with downhole submersible pumps to maximise field production rates. Initial production from the field is estimated at a gross rate of 22,500 barrels of oil per day (“bopd”) (5,062 bopd net to Ithaca). Applied Drilling Technology International (a division of Transocean  Drilling UK Ltd) will manage the programme on a ‘turnkey’ basis which is anticipated to last approximately 180 days.  Subsea work will follow in Q3 2011, to install field pipelines and subsea manifolds. The Company will update the market as and when drilling and/or completion work reaches key milestones.  
The FPSO ‘BW Athena’ is at dockside in Dubai and preparation works have commenced to re-certify existing equipment and install new equipment.  In Q2 2011 the vessel will be ‘dry docked’ for the installation of a turret mooring section amidships, extending the FPSO by approximately 65ft.  Steelwork for the mooring section is being prepared alongside the dry dock. All work is anticipated to be completed in Q3 2011 allowing the vessel to return to UK 
waters and arrive on location at Athena at end Q3 2011.  Installation of the FPSO vessel to the mooring buoy, as well as, hook up and commissioning will be completed in anticipation of targeted first oil in Q4 2011. Both BW Offshore’s Site Office and the Ithaca Representative’s Office in Dubai are manned and operational.  
John Woods, Ithaca’s Chief Development Officer, commented:  
“The drilling programme at Athena has commenced on schedule enabling the rig to complete its scope of work ahead of other field construction activities. Work on the Athena field remains very much in line with targeted first production from the field in Q4 this year at a gross rate of 22,500 barrels of oil per day. Work on the FPSO in Dubai and the other project construction activities have also all commenced on  schedule and within budget giving the project team an excellent start to the New Year.” 
The Athena Joint Venture Partners are Ithaca (operator, 22.5%), Dyas UK Ltd (47.5%), EWE Aktiengesellschaft (20%) and Zeus Petroleum Limited (10%). 

0 comments:

Post a Comment

 
Copyright © 2011. Maritime Press Clipping . All Rights Reserved
Home | Company Info | Contact Us | Privacy policy | Term of use | Widget | Site map
Design by Herdiansyah . Published by Borneo Templates