Dec 15, 2010
Statoil: Kristin, Tyrihans production stopped in Norwegian Sea
In connection with a routine inspection of the Kristin platform in the Norwegian Sea at the end of last week, a high temperature was discovered on the outside of an exhaust duct on one of the gas turbines.
The temperature was higher than considered acceptable and a decision was taken to stop production during Sunday, December 12.
Work is under way to rectify matters. It is expected that production can be resumed by the end of December.
The Kristin platform lies in the south-western area of the Halten Bank and produces gas and oil/condensate from the Kristin and Tyrihans fields.
The shut-down will entail a deferment in production of daily volumes corresponding to a total of 100,000 barrels of oil equivalent (boe) from the two fields.
Source: Press release
Category:
Offshore and Energy
Subscribe to:
Post Comments (Atom)
0 comments: